題目
材料全屏
58

【單項選擇題】

What are the equivalent units for closing work-in-progress at the end of the month?

A

Material??????? Conversion costs

25 litres??????? ?25 litres

B

Material?????? Conversion costs

25 litres????????50 ?litres

C

Material????????? ?Conversion costs

50?litres?????????? 25 litres

D

Material???????????Conversion costs

50?litres????????????50 litres

掃碼查看暗號,即可獲得解鎖答案!

點擊獲取答案
考點:Chapter11Processcosting

Work in progress=800 litres input - 250 litres to finished goods =50 litres

Equivalent litres for each cost element are as follows.

???????????????????????????????????????????????????????????? ?? Material??????????????????????????????????????????????????????????? Conversion costs

?????????????????????????????????????????????????? %????????????????????????? Equiv. litres?????????????????????? ? ???? %????????????????????????? Equiv. litres?

50 litres in progress?????????????????? 100??????????????????? ?????? 50?????????????????????????????????????????50???????????????????????????? 25

多做幾道

What was the actual usage of direct material during February?

A

800 kg

B

1,000 kg

C

1,200 kg

D

None of these

What was the selling price variance for February?

A

$120 (F)

B

$900 (A)

C

$1,200 (A)

D

$1,200 (F)

What was the sales volume profit variance for February?

A

$900 (F)

B

$1,200 (F)

C

$900 (A)

D

$2,100 (A)

材料全屏
30

【簡答題】

From the information provided calculate

(i)?The actual price paid per kg for the direct material?

(ii)?The standard quantity that should have been used for actual production.

Which of the following is likely to lead to the variances stated above?

A

lower quality direct material has been purchased

B

?higher quality direct material has been purchased